Saturday, 1 August 2026

Wallers' update

 
WALLERS' NEWS

The Nidderdale wallers have been busy at Breaksfold Farm over the last two Wednesdays. They are going to have their very own blog entry this weekend to make sure that you are all kept up to date, so read on to see their progress.....

22nd July 2026 by Barry:

Benign conditions greeted six of us as we arrived early on North Moor Road, cloudy but warm with barely any wind. The Knabs Ridge turbines remained motionless all day. Everyone took up preferred positions along the working stints. Rod & Simon added five courses and topped out the first five metres, then assisted Dave & Andy on the next, while Barry & Wayne brought the end section up to meet it. Much hammer work was again needed to fashion level courses out of unpromising material, but steady progress was made with the prospect of completing this section next time. Curlews and Oyster catchers alerted us to several fly-overs by red kites, else all was calm. Very warm work when the sun did break through on occasions, so a 2.30 finish was agreed.

Fine tuning at the end of the day

Lots of small stones, not the easiest to work with

Looks pretty neat and tidy

To level up and top out next week

29 July 2026 by Graham:

It was a warm and often cloudy day for walling, excellent for the six of us continuing with the task at Breaksfold - fortunately nowhere near as oppressive as some previous weeks. This being Wayne's third week of walling, he first spent a morning with Graham, learning how to dismantle the next four yards of wall, whilst the rest of the group finished what was left over from last week. 

By lunchtime their eight yard section had been brought up to height and topped out, whilst  Wayne and Graham had done the reverse and  taken down their section to soil level.  In the afternoon, Wayne moved on to another new task, namely that of laying foundations of the dismantled section.  Graham and Rob dismantled another four yards of wall whilst  Andy and Duncan moved mountains, tidying up all the loose stone from previous weeks' sessions; quite some task. Overall another productive week's walling and some excellent training for Wayne.

Wayne looks at the morning's work ahead of him

By lunchtime the wall has disappeared

Again by lunchtime, last week's wall had been completed

Rob looks at his afternoon's dismantling task

 Dave and Wayne completed the foundations

End of day and time to pack up

Tuesday, 28 July 2026

Yates House, Braithewaite: 28-0702926

 

The window is opening soon

As July came to an end this week the NCVs were preparing for the next window of tree tube recycling. It made a welcome relief from balsam pulling and was a job that they were well used to, having carried out this task earlier in spring on a number of occasions.

Yates House was a new venue - always interesting to see - and the job mainly involved the removal of hedging spirals rather than many of the usual tubes. 

Ok - the scene is set - let's look at this week's pictures to see how well they got on....

This was the first hedge
encountered. 300m of spirals
to be removed.

Below it was the plantation.
Here the majority of trees
were still too small for tube
removal. Only the 
dead trees were detubed.

Everyone needed to get down 
on their kneelers to work the hedge.

Before...

...and after.

Often the tubes ended up like this.
Not good!

Others behaved themselves
and lay quietly awaiting collection.

Paul and Will were collecting
the discarded spirals and canes.

Occasionally there was
a surprise to be found.
Here was a new species of hawthorn.
Crataegus twirlywhirlycus.

And the odd petrified frog.
Crisp anyone?

Now and again we came 
across tree cages. Osian
made short work of these.



Oh heck - these three trees
don't look in peak condition!

By coffeetime the first 
hedge was done...

...and everyone was delighted
by the array of cakes that were
 supplied by landowners Sue and Andy.

Thanks both - MUCH appreciated.

A small team was then left 
to deal with any tube removal
in the plantation whilst the
rest marched up the hill
with the the Grand Ol' 
Duke of York.

Here they started wok 
on the 100m of more 
restricted hedge.

It was at this point that Will
was given the bad news that
this little chap had got into 
his rucksack and eaten his 
lunchtime pork pie. 
Oh deary me. Naughty boy!!!!

Slowly but surely the
spirals succumbed...

...to allow the gang to once more
get behind the Grand Ol' Duke 
as he led them down again.

The bags of collected material
were loaded into Liz's trailer...

...and then everyone went and 
had lunch in a beautiful garden.
What's not to like about volunteering?!

And some other walling news that we have been waiting for the go-ahead from Menwith Hill to publish from 3rd June....
Wallers' update
by Graham

Following on from three weeks ago, when the wallers prepared the Menwith Hill wall for this year's Earth Day rebuild on the 3rd June. The group welcomed five volunteers from the base in the morning and another seven in the afternoon to have a go at walling.  As in previous years, the volunteers were an enthusiastic bunch who picked up the basics very quickly and produced a very respectable bit of walling . 
Overall we worked in five groups over 25 yards or so of wall,   topping off 5 yards and adding several courses beyond.  This was despite some heavy rain at times, although never  persistent enough to curtail the event. The hosts had kindly laid on pizzas for lunch, which was very much welcomed together with a visit and personal thankyou from the RAF Cdr,  a personal note of thanks from the Base Director and an inscribed celebratory walling hammer which has now been incorporated into the wall  (see photo).  Our thanks to all the team at Menwith Hill for their hospitality and for another successful walling day.

Tuesday, 21 July 2026

Limley Farm: 21-07-2026

 

Anyone for balsam pulling?

You too could enjoy spending time like this!

Or not. It's up to you. But, according to the latest research published in a highly regarded scientific journal, the weekly act of working hard in hot weather, scrambling along a river bed, pulling up and crushing balsam, "allows the body to purge itself of all toxins and leaves participants with a wonderful sense of wellbeing when the job is done." (Snedworth , 2026, p.42) 

A small band of NCVs decided to try out this activity to see if Samuel Snedworth's claims were true. I have to say - they had their doubts. Here are some pieces of evidence of what ensued during this experiment.

Not much sign of HB
yet. Not much water 
in the river either.

Is this some?
NO! Leave it alone.
It is a beautiful giant bell flower.

Uh oh. There is definitely some here.

There was a competition
for the largest plant found.

What about this one?
No. Ftoo diddly.

Well - what about this one?
No. Still too feeble.

What about mine?
Oh yes!! Now that is what you call
a good size for an HB plant.
Dawn wins the prize.

Lunch in the sun provided a
little respite for the legs,
but not from the heat.

The hunt continued until...

...the skull of a previous HB hunter
 was spotted - clearly an NCV who 
had been left behind last year.
 Nobody could face going any 
further after that!!!.

At the end of the day Liz asked the NCVs to complete a set of forms to provide Professor Snedworth with some useful feedback upon which he might take his research forward. When Liz gathered in the papers she decided that it might not be such a good idea to forward them to the Prof. It was highly likely that he would be offended by the, often less than polite, responses. The NCVs did not feel any benefits what-so-ever from this undertaking and had made this crystal clear in their feedback.

Ref. List

Snedworth, S. (2026) 'Balsam and the Body Beautiful' in All Things Environmental Issue.45 pp. 36-50


Last Thursday a select band of 3 of the rights of way team joined Liz on a bridge survey day in the Thornthwaite and Padside area. 6 bridges were checked in very hot conditions and all needed cleaning. 

Here they are in action....

We walked over bridge 
number one without realising -
a stone vehicular structure.
Did anyone bring the Pledge?

Bridge 2 involved a long walk
but was easy to spot.
A metal suspension bridge - 
with rotten rails underneath 
the floorboards. Oh dear!

Bridge 3 involved a very long walk
 across a field of waist high thistles.
Ouch!

Once we arrived we discovered
 that the three stone slab bridge 
had lost a slab into the beck.

Bridges 4, 5 and 6
were all similar wooden
structures in need of encroaching 
vegetation removal and 
moss scraping and brushing. 

And finally - from last Wednesday....

A Wallers' Update from Breaksfold Farm
by Graham

Another good turnout at Breaksfold Farm; seven in all. A dull start had been forecast but the mist and cold were not expected. Hence an "unhappy" Graham in fleece and wooly hat! The sun didn't appear until the end of lunchtime, at which point it came out with a vengeance.  

Grumpy Graham. Heat wave! 
What heatwave?

There was excellent progress on the new section with foundations completed by coffee break and then a further four courses completed.  

Duncan checks the foundations

 Nice looking wall, just the 
cover band and toppers to add.

Work on the longer section was slower going, requiring half a dozen or so thin, time consuming, courses. Hopefully next week will see the toppers added. As usual lovely views, inquisitive sheep and birds singing.

End of day looking towards 
the new Blubberhouses bypass.

And the wall from the other side!

Impressively straight!